Update: Road Improvement Project to Begin 6/26
Posted on: June 24, 2020 - 8:46am
The Township’s 2020 road improvement project is scheduled to begin June 26, 2020. The contract for the work was awarded to Alan Myers Construction. Township representatives will be on-site to inspect the work. Milling will start on Friday, June 26 according the schedule below. Once milling is completed, the roads will be paved in the same order.
Notices will be hand-delivered by Alan Myers to all properties along these roads. Weather and/or unexpected issues could result in changes to the schedule. Affected roads will be open to local traffic and emergency vehicles.
Monday 6/29
Copper Mine Road
Leon Avenue
Lee Road
Driftwood Drive
Tuesday 6/30
South Midland Avenue
Oakdale Avenue
West Sunset Avenue
Oaklyn Avenue
Wednesday 7/1
Parklane Drive
Fox Road
Landis Mill Road
Kingston Circle